Free Practice Exam - PMI-RMP
Question 1 of 15
There are several processes endorsed in Project Risk Management - each one with its own inputs and outputs.
Do you know what the output is from the Identify Risks process?
Project documents updates
Change requests
Risk management plan
Risk register
That was the correct answer, well done!
Sorry, that was the wrong answer
At the heart of Project Risk Management is the Identify Risks process which takes multiple inputs but ends with the Risk Register output.